New Outfall Pipe

We have now completed the installation of the new outfall pipe at Shipwrights Point, a key part of our commitment to improving environmental outcomes in the region.

  • The Horizontal Directional Drilling site has been cleared and levelled, and the grass is taking well
  • The outfall pipe, located 260 metres offshore at a depth of 13 metres, will provide improved dilution and dispersion, supporting better environmental outcomes.
New Sewer Pump Station

As part of the project, a new pump station and 79-kilolitre emergency storage tank will be installed near the existing Geeveston Sewage Treatment Plant.

  • This tank will help reduce the frequency and volume of overflow events.
  • Site office and laydown area establishment work will begin in April 2026
  • Construction is expected to commence in July 2026
New 4.3. kl Pipeline

Design work for the new 4.3-kilometre pipeline along the Huon Highway, connecting the Geeveston Sewage Treatment Plant to Shipwrights Point, has been completed.

  • We are finalising construction contracts
  • Major pipeline construction is scheduled to begin in July 2026.
Staying Informed

To keep up to date with this project, please bookmark this page, or if you would like to know more, please contact our Capital Engagement team on 13 6992 or email capitalprojects@taswater.com.au.

We appreciate the community’s support as we deliver this essential upgrade to protect the environment and support the region’s future.