Skip to main content

About

What's this project all about?

Orford’s existing sewerage network was designed and built decades ago for a much smaller town. Nowadays, the network will often overflow as stormwater enters the sewerage system, much of it from private property. This project will reduce the frequency, volume and impact of those overflow events, and improve TasWater’s protection of the local community and environment.

Currently, all of Orford’s sewage is pumped through one ‘daisy chain’ to the Orford Sewage Treatment Plant, via a sewer main near West Shelly Road. Instead, the network will be split in two to reduce these loads. We will construct a new pressurised ‘rising’ main along Walpole Street and Rheban Road to the treatment plant. Five of Orford’s sewage pumping stations (SPS) will be upgraded with new underground emergency storage tanks and pumps. New rubber seals around wet wells will prevent odour, and electrical upgrades, new lighting and improved vehicle access will also mean our people can respond faster in emergencies.


Where are we working?

  • The Hedge SPS on the foreshore walking track north of Millington’s Beach, by the Orford Bird Sanctuary
  • The Prosser Bridge SPS on the north-east shore
  • The Our Park SPS at the northern end of Walpole Street, including a new above-ground electrical switchroom
  • The Wade Bridge SPS by Orford Rivulet
  • The West Shelly SPS off West Shelly Road
  • A new pipeline along Walpole Street and Rheban Road.

Construction

There will be construction activity throughout Orford during most of 2024, including excavation, truck movements, heavy equipment, many vehicles and workers. Most work will take place Monday to Friday and we are targeting times outside the peak summer and holiday periods, where possible.

While TasWater and our contractors make every effort to reduce our impact on the surrounding community, it is our hope that locals will understand there will be some short-term disruption to deliver a long-term benefit, and that some areas will look a little different once our work is complete.

Great care is being taken to preserve trees and TasWater has engaged professional arborists to assess each site, so we can design our infrastructure around existing trees wherever possible. The goal is to keep the most established specimens and species that provide wildlife habitat.

New vent stacks

We understand there can be concerns about odour from vent stacks, but properly designed, installed and maintained vent stacks actually prevent odour from affecting the community. Each SPS and the new rising main will need vent stacks to function properly. Their location is set by the local geology, the height of the infrastructure and our design requirements.

Some of Orford’s old vent stacks have not been effective, primarily because they are not tall enough. Our new vent stacks will be nine metres tall, releasing any odour well above head height. They are manufactured from superior materials to the old vent stacks, are more rust resistant and require less maintenance. Each will also have a new stainless steel ‘whirly bird’ fitted, to draw and disperse air from the system (an example of the new vent stacks can already be seen on Manning Drive on the path to the historic Prosser Bay quarry). Vent stacks constructed in this way are common infrastructure throughout Tasmania.

TasWater is confident that by venting the sewer at nine metres above ground, from new SPS with effective seals, we will provide a better odour management solution than anything currently in Orford.

News

Updates

Timeline

  • Timeline item 1 - complete

    2023

    Project in design and development phase.

  • Timeline item 2 - complete

    November 2023

    We are working with Aboriginal Heritage Tasmania and consultant archeologists on investigations for our project throughout Orford, where Aboriginal heritage is known to be widespread. This process is required under Tasmanian law. Any test pits we dig must remain open until approval to backfill is given by the State Government. Some remain in Our Park on Walpole Street.

  • Timeline item 3 - complete

    March 2024

    Work is beginning on the first stages of our project, including a site office near the corner of Rheban Road and Wielangta Road.

  • Timeline item 4 - complete

    April 2024

    Construction of the new rising main pipeline will commence - starting near the sewage treatment plant on Rheban Road and moving towards Walpole Street. Construction will last approximately 18 weeks.

  • Timeline item 5 - complete

    May 2024

    Work at the Prosser Bridge and Heathers Sewage Pump Stations will commence.

  • Timeline item 6 - complete

    July 2024

    Work at Our Park Sewage Pump Station will commence.

  • Timeline item 7 - active

    August 2024

    Work at West Shelly and Wade Bridge Sewage Pump Stations will commence

  • Timeline item 8 - active

    September 2024

    During the first two weeks of September we will be undertaking works to widen the access path between the West Shelly SPS and Wade Bridge SPS.

    Pedestrian detours will be in place during these works, and will continue intermittently until March 2025. Signage will be in place to direct pedestrians.

  • Timeline item 9 - incomplete

    Mid 2025

    Project Completion

Maps

Project maps


Since creation, the palawa have lived here in lutruwita - Tasmania. Over 2,000 generations of Aboriginal families have cared for this Country, looking after its lands, seas, skies and waterways.

In the spirit of respect and gratitude, TasWater acknowledges the Tasmanian Aboriginal community as the traditional and ongoing custodians. We pay our respects to them, their culture and to elders past and present. We also acknowledge any Aboriginal and Torres Strait Islander people who are here with us today.

TasWater commits to working collaboratively and respectfully with the Tasmanian Aboriginal community to protect and sustain the precious resources on this ancient land for future generations.

Contact Us

Have questions or want to learn more about a project, contact us below:

Contact Information
Phone 13 6992
Website www.taswater.com.au
In writing

GPO Box 1393, Hobart TAS 7001