Construction Update 21 November

21 November 2024

Pipeline installation is progressing well along the Tasman Highway with key infrastructure being installed over the coming weeks.

Works at the Murray Street Sewage Pump Station are progressing slower than expected due to the rocky ground conditions. The team is working hard to complete the works as efficiently as possible, however rock breaking activity is likely to continue for at least approximately another two weeks.

We understand that these works are happening close to residents, and we thank the community for your continued support and patience during this project.