News

Construction Update -Temporary Road Closure Station Road

24 February 2026

As part of the next stage of construction for the Dover Foreshore Sewer Upgrades, there will be temporary traffic changes on Station Road:

  • When: Full closure from Tuesday 10 March 2026 to Friday 13 March 2026
  • Where: Station Road will be closed between 21 Station Road and 22 Station Road.
  • Access: Traffic will be detoured via Chapman Avenue, with restricted access available for affected residents.
  • What: This closure is required to install new gravity sewer mains

Access to some properties may be restricted during this time and partial road closures required, resulting in some delays for traffic. There may also be some construction-related noise while the works are taking place. Please plan your journey in advance to factor in any minor delays.

This upgrade is part of TasWater’s commitment to investing in new and improved sewerage infrastructure projects across Tasmania. These projects will provide improved public health and environmental compliance and ensure our assets deliver reliable service for future generations. Thank you for your patience and understanding as we continue our work to improve your sewer network.

For more information about this project please contact our Community Engagement team, on 13 6992 or email capitalprojects@taswater.com.au.