News

Queenstown Water Main Renewal - Construction Update

4 March 2025

We are pleased to confirm that Stage 3 is complete. We have successfully renewed water mains on Powell Street, Mellor Street, Alfred Street, McNamara Street, Cutten Street, Brooklyn Street, Crotty Street, Bowes Street, Dixon Street and Counsel Street. Residents of these streets have been switched over to the new water mains with great results for cleaner water.

Stage 4 is currently underway and this mean that new water mains on Henry Street, Urquhart Street, Grafton Street, Pillinger Street, Douglas Street, Braddon Street and O’Halloran Court are currently under construction.

Stage 5 on Murray Street, Lynchford Road, Mathew Street and Bury Street is on track to commence in March.

We would like to thank the town and residents for their co-operation and patience as we continue our work to provide access to a clean and reliable supply of drinking water.