Regional Towns Water Supply Program – Construction Update | December 2025

17 December 2025

As part of TasWater’s commitment to a better water future for all Tasmanians, we’re investing in significant improvements to water capacity and supply across our regional towns. We’re continuing to make great progress on the Regional Towns Water Supply Program, helping to deliver safe, reliable drinking water for more Tasmanians.

Better Water for Bothwell and Oatlands
Bothwell Water Treatment Plant Replacement Project
  • Construction is now underway on a brand-new water treatment facility to replace ageing infrastructure in Bothwell.
  • The project includes a connection to the Southern Highlands Irrigation Scheme and expanded storage capacity, delivering better water quality and improved water security for Bothwell, as well as supporting the surrounding agricultural community.
New Bothwell WTP - access road and early works

New Bothwell WTP - access road and early works

New Bothwell WTP – works underway

New Bothwell WTP – works underway

Oatlands Water Treatment Plant Replacement Project

  • Construction began in October to replace the existing water treatment plant at Oatlands.
  • The new facility will provide better water quality and more reliable water services for Oatlands residents into the future.
The existing Oatlands Water Treatment Plant site

The existing Oatlands Water Treatment Plant site

Oatlands WTP - access road and site establishment works

Oatlands WTP - access road and site establishment works

New Reservoir projects

Dover

  • Work is well underway on the additional reservoir at Dover, with concrete poured in early December to construct the reservoir base.
  • Our crews and contractors reached this significant milestone by working from sunrise to sunset to safely complete this major construction activity.
Sunrise over Dover from the reservoir

Working in some of Tasmania’s most beautiful spots – what a view while we get the job done!

Birds eye view of the Dover Reservoir concrete being poured

New Dover Reservoir - base concrete pour underway

Franklin

  • Increased water storage for Franklin. Progress continues at Franklin, with the temporary tank now commissioned and supplying water to the community.
  • Demolition of the old reservoir is scheduled to begin first thing in the New Year.
An overview of the works underway at the Franklin Reservoir

Franklin Reservoir - works underway to prepare for demolition of the old tank

What to expect during construction
During works, community members may notice increased heavy vehicle movements, construction noise and temporary traffic arrangements as required.

Please follow all signage and directions in place to help keep the community and our people safe while this essential work is completed.

These upgrades are part of our ongoing commitment to delivering better water for regional Tasmania. We’ll continue to keep you informed as we reach key milestones in each town.