About

Project Overview Video

What's this project all about?

As part of TasWater’s commitment to investing in new and improved sewerage infrastructure to cater for Hobart’s future growth, we are delivering one of our most significant projects to date.

This project combines the following 3 separate, but interconnected projects:

Once we have completed these works, we will begin decommissioning the existing Macquarie Point Sewage Treatment Plant.

The existing Selfs Point Sewage Treatment Plant was built in 1972 to support the treatment of Hobart’s wastewater. The plant currently treats around nine megalitres of wastewater from Hobart suburbs including Lenah Valley, New Town, Mount Stuart, Sandy Bay, Dynnyrne, Tolmans Hill, Mount Nelson, and Taroona. That’s approximately 110,000 average baths a day!

The expansion and upgrading of the existing plant, combined with the future decommissioning of the Macquarie Point Sewage Treatment Plant, will deliver improved environmental outcomes and the new state-of-the-art facilities and treatment technologies will enable us to treat up to 25 megalitres of Hobart’s wastewater per day.

Preparation for the decommissioning of the existing Macquarie Point Sewage Treatment Plant and construction of a more compact state-of-the-art pump station at Macquarie Point will be undertaken while we upgrade and expand the existing Selfs Point Sewage Treatment Plant.

The Macquarie Point Sewage Treatment Plant currently treats wastewater from residential, business, and light industrial customers within North Hobart, West Hobart, Glebe, South Hobart, Battery Point and the Hobart Central Business District (CBD).

As part of this transformative project, we will be building a new 4.3 kilometre pipeline to connect the new pump station at Macquarie Point and the future Selfs Point Sewage Treatment Plant at New Town Bay.

By streamlining the operation of these two plants into a single modern facility, we will help improve marine health by removing tonnes of nitrogen and phosphorus from the Derwent River every year.

Updates

Community Information Session

We thank the visitors who came along to the project’s information session Saturday 30 November 2024. The information session was an opportunity for the community to meet with our project representatives and learn more about the project. We have included the information we had on display.

Latest News

Timeline

Timeline

  • Timeline item 1 - complete

    Early 2023

    During late 2023 we undertook preliminary survey works, including geotechnical investigations. We will continue with these activities around the port area during March 2024 as part of our design works for a new pipeline that will be built between our Selfs Point and Macquarie Point facilities.

  • Timeline item 2 - complete

    November 2023

    In November 2023, we submitted the Macquarie Point Sewage Pump Station & Emergency Storage Environmental Impact Statement Report to the Environmental Protection Agency. After the public exhibition period during November and December 2023, the EPA formally approved this part of the project in February 2024.

  • Timeline item 3 - complete

    December 2023

    In late December 2023, the Development Application was lodged with City of Hobart for the new Selfs Point Sewage Treatment Plant at New Town Bay, next to our existing plant.

  • Timeline item 4 - complete

    Mid to late 2024

    During April and May 2024, we continued with the early phases of setting up our future construction site at Macquarie Point.

  • Timeline item 5 - complete

    June 2024

    The Hobart City Council advertised the Development Application for the Selfs Point Sewage Treatment Plant expansion. The Environmental Impact Statement was advertised by the Environment Protection Authority and is now closed for public comment.

  • Timeline item 6 - complete

    July- September 2024

    The Environment Protection Authority approved the Environmental Impact Statement for the proposed expansion of the Selfs Point Sewer Transformation Project. The Hobart City Council approved the Development Application for development on the land at Selfs Point associated with the Selfs Point Sewer Transformation Project.

    Early site establishment works undertaken, including new project office and amenity buildings.

  • Timeline item 7 - active

    October 2024

    Vegetation clearing along the Lower Domain Road is underway in preparation for construction of the new sewer pipeline.

    Vegetation clearing onsite at Selfs Point. The site is currently being prepared for piling works which will commence at the end of month.

  • Timeline item 8 - active

    December 2024

    Most of the earth compacting works have been completed. Piling works are now underway across the site to install the concrete piles that will support the main structures of the new facility.

Map

New sewer pipeline alignment map

New sewer pipeline alignment map

Construction of the new sewer pipeline will commence in early 2025.

We will be working in sections to minimise disruptions where possible and we will ensure any changes to traffic and pedestrian access is communicated well in advance.


Project videos

Project construction images

View our latest construction images and project concept images

Have your say...

We welcome your feedback about the Selfs Point Sewer Transformation project.