News

Out-of-Hours Construction 2025

25 June 2025

As part of the ongoing Selfs Point Sewer Transformation, major construction activities are progressing at the site, including large concrete pours for the new facility.

Due to the size and complexity of these pours—particularly for water-retaining structures—some work is required outside standard construction hours. This may involve early morning or evening activity to allow for extended pour times and proper curing.

While we understand that out-of-hours work can cause disruption, particularly in terms of noise, we’re taking steps to minimise any impact on nearby residents.

The current schedule for these works is available in the table below and will be updated regularly to reflect any changes.

We appreciate the community’s continued patience and understanding as we deliver this critical upgrade.

For further information, please contact our Capital Engagement team on 13 6992 or via email at capitalprojects@taswater.com.au.

Planned works

Saturday 13 September 2025

Out-of-hours works 13 September 2025

Excavation and pipe installation from 8 am to 5 pm.

Saturday 20 September 2025

Out-of-hours works 20 September 2025

Excavation and pipe installation from 8 am to 5 pm.

Wednesday 2 July 2025

Out-of-hours works 2 July 2025

Location: Selfs Point Sewer Transformation construction site 5am to 7am