We’re making steady progress on the Selfs Point Sewer Transformation – a vital project helping to deliver a healthier Derwent for Hobart’s growing future.

As part of the next stage, we’ll soon begin major construction activities, including large concrete pours needed to build the new facility at Selfs Point. Concrete pours and curing times associated with large water retaining structures can be lengthy, which means some work will take place outside our usual construction hours—early in the morning or into the evening.

We know out-of-hours works can cause inconvenience, especially due to noise, and we’re committed to minimising any disruption as much as possible.

You can view our current schedule for these works in the table below. We’ll keep this information updated regularly, so we encourage you to check via the QR coded for the latest details.

We appreciate the understanding and patience of our local community while we undertake this important work.

For more information about this project please contact our Capital Engagement team, on 13 6992 or email capitalprojects@taswater.com.au.

Planned works

Thursday 15 May 2025 05:30 am

Out-of-hours works - 15 May

Location: Selfs Point Sewer Transformation construction site 10 Selfs Point Road, New Town TAS 7008

Tuesday 20 May 2025 05:00 am

Out-of-hours works - 20 May

Location: 5am – 7am and 6pm – 9pm Selfs Point Sewer Transformation construction site 10 Selfs Point Road, New Town TAS 7008

Wednesday 21 May 2025 05:00 am

Out-of-hours works - 21 May

Location: 5 am to 7 am and 6 pm to 9 pm Selfs Point Sewer Transformation construction site 10 Selfs Point Road, New Town TAS 7008