What's this project all about?
Stage 4 of our Regional Towns Water Supply Improvement program included the construction of a new water supply pipeline and pump station, connecting existing water infrastructure at Ellendale with the Fentonbury water treatment plant. Works commenced in July 2024 and the pipeline took approximately 9 months to complete.
The new pipeline will supply water to the Ellendale community from early September 2025 and will eliminate the need for seasonal water carting and ensure consistent, high-quality water for Ellendale residents year-round.
Thank you to the Ellendale, Fentonbury, and Westerway communities for your patience and support throughout this project as we work together towards a better water future for all Tasmanians.
Updates
Project updates
Project construction images
Timeline
Project timeline
-
Timeline item 1 - complete
Phase 1 Construction
Commenced mid 2024
-
Timeline item 2 - complete
Ellendale to Fentonbury Pipeline Project
Construction commenced July 2024
-
Timeline item 3 - complete
Ellendale to Fentonbury Pipeline Completed
Construction of the new pipeline was completed in late March 2025
-
Timeline item 4 - complete
Fentonbury - New Pump Station
Construction commenced September 2024
-
Timeline item 5 - complete
Fentonbury Pump Station completion
Construction of the new pump station was completed in June 2025
-
Timeline item 6 - complete
Ellendale Water Supply Pipeline
First supply of water to the Ellendale community commenced in early September