About
What's this project all about?
As part of TasWater’s commitment to delivering a better water future for all Tasmanians, we’re investing in significant improvements to support the water needs of our regional towns. Phase 2 of the Regional Towns Water Supply Improvement program includes the construction of new water treatment plants for the Bothwell and Oatlands communities, with works starting in October 2025. Once the new plants are in operation the old treatment plants will be decommissioned.
These upgrades will improve reliability of water supply, water quality, and increased capacity to meet current and future community needs.
What to expect during the works
During construction, you may notice more heavy vehicle movements in the area and temporary traffic arrangements as required. Please follow all signage and directions and thank you for helping to keep our people safe as they complete this essential work.
Timeline
-
Timeline item 1 - complete
Oatlands - Planning and investigation
Surveying, soil tests, and investigations to inform design commenced in October 2024
-
Timeline item 2 - active
Oatlands Water Treatment Plant Replacement Project
Construction of a new water treatment plant for Oatlands will begin in October 2025.
-
Timeline item 3 - incomplete
Oatlands - Building Works
Construction of the new building is scheduled for completion by June 2026.
-
Timeline item 4 - incomplete
Oatlands - Construction Complete
Completion of the new water treatment plant is scheduled for November 2026.
-
Timeline item 5 - incomplete
Oatlands Project Operational (first water delivery)
Final completion in readiness for the first delivery of water to the community is scheduled for February 2027.
-
Timeline item 6 - complete
Bothwell - Planning and investigation
Surveying, soil tests, and investigations to inform design commenced in October 2024
-
Timeline item 7 - active
Bothwell Water Treatment Plant Replacement Project
Construction of a new water treatment plant for Bothwell will begin in October 2025.
-
Timeline item 8 - incomplete
Bothwell - Building Works
Construction of the new building is scheduled for completion by June 2026.
-
Timeline item 9 - incomplete
Bothwell - Construction Complete
Completion of the new water treatment plant is scheduled for November 2026.
-
Timeline item 10 - incomplete
Bothwell Project Operational (first water delivery)
Final completion in readiness for the first delivery of water to the community is scheduled for February 2027.